ITAC Assessment: MO0002
ITAC logo
ITAC Assessment: MO0002
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product ELECTRIC METER EQUIPMENT
NAICS
n/a
SIC 3613: Switchgear and Switchboard Apparatus
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area
n/a
Annual Production 1,000,000
pieces
Production Hrs. Annual 4,200
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,600 1,340,856
kWh
LPG $38,391 11,450
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,767 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,351

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings
01 2.2511: Insulate bare equipment $7,308 $18,163 - $7,308
-
MMBtu
02 2.2212: Use minimum safe oven ventilation $4,111 $760 $(-94.0)
(-1,465)
kWh
$4,205
-
MMBtu
03 2.4231: Reduce the pressure of compressed air to the minimum required $3,186 $100 $3,186
50,410
kWh
-
04 2.2511: Insulate bare equipment $2,183 $5,826 - $2,183
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $1,165 $150 $1,165
18,464
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $814 $930 $814
12,896
kWh
-
TOTAL RECOMMENDED $18,767 $25,929 $5,071
80,305
kWh
$13,696
-
MMBtu
TOTAL IMPLEMENTED $4,351 $250 $4,351
68,874
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs