| Assessment Year | 2026 |
|---|---|
| Principal Product | Medical Injection Molding |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 35 |
| Plant Area |
23,000
ft2
|
| Annual Production | 6,000,000
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,556 | 1,118,040 |
kWh
|
$0.061 |
| Electricity Demand | $38,017 | 2,802 |
kW-mo/yr
|
$13.57 |
| Electricity Fees | $19,592 | - |
|
- |
| TOTAL YEARLY COSTS | $126,165 | |||
| RECOMMENDED SAVINGS* | $19,420 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3137: Use power during off-peak periods | $3,799 | - | - |
$3,799
-
kW-mo/yr
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,098 | $1,980 |
$4,323
70,876
kWh
|
$2,775
-
kW-mo/yr
|
|
| 03 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $253 | $80 |
$154
2,530
kWh
|
$99
-
kW-mo/yr
|
|
| 04 | 2.6218: Turn off equipment when not in use | $2,046 | $2,600 |
$2,046
33,541
kWh
|
- | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $625 | $1,200 |
$381
6,244
kWh
|
$244
-
kW-mo/yr
|
|
| 06 | 2.7425: Clean or color roof to reduce solar load | $5,599 | $23,200 |
$3,410
55,902
kWh
|
$2,189
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $19,420 | $29,060 |
$10,314
169,093
kWh
|
$9,106
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs