| Assessment Year | 2025 |
|---|---|
| Principal Product | Secure drug delivery devices |
| NAICS | 339112: Surgical and Medical Instrument Manufacturing |
| SIC | 3841: Surgical and Medical Instruments and Apparatus |
| Sales Range | $10 M to 50M |
| # of Employees | 158 |
| Plant Area |
35,100
ft2
|
| Annual Production | 8,000,000
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $135,251 | 2,182,920 |
kWh
|
$0.062 |
| Electricity Demand | $52,034 | 4,016 |
kW-mo/yr
|
$12.96 |
| Electricity Fees | $31,776 | - |
|
- |
| TOTAL YEARLY COSTS | $219,061 | |||
| RECOMMENDED SAVINGS* | $152,870 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,870 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,818 | - | - |
$2,818
-
kW-mo/yr
|
|
| 02 | 2.2211: Use optimum temperature | $31,534 | $960 |
$20,119
324,499
kWh
|
$11,415
-
kW-mo/yr
|
|
| 03 | 2.6218: Turn off equipment when not in use | $10,560 | $7,300 |
$10,560
170,329
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,118 | $11,168 |
$3,902
62,939
kWh
|
$2,216
-
kW-mo/yr
|
|
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $905 | $4,156 |
$581
9,371
kWh
|
$324
-
kW-mo/yr
|
|
| 06 | 2.9114: Use solar heat to make electricty | $78,625 | $364,596 |
$30,472
491,476
kWh
|
$48,153
-
kW-mo/yr
|
|
| 07 | 2.7232: Replace existing hvac unit with high efficiency model | $22,309 | $111,252 |
$14,224
229,424
kWh
|
$8,085
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $152,870 | $499,432 |
$79,858
1,288,038
kWh
|
$73,012
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $32,870 | $118,552 |
$24,785
399,753
kWh
|
$8,085
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs