ITAC Assessment: MI0446
ITAC logo
ITAC Assessment: MI0446
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Recycled Tires
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 120
Plant Area 50,000
ft2
Annual Production 80,000
ton
Production Hrs. Annual 8,730
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $758,051 12,473,492
kWh
Electricity Demand $444,900 29,660
kW-mo/yr
Electricity Fees $97,785 -
Waste Disposal Costs
Water Usage $2,455 273
Tgal
TOTAL YEARLY COSTS $1,303,191
RECOMMENDED SAVINGS* $154,847 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
01 2.4322: Use or replace with energy efficient substitutes $103,738 $390,000 $75,478
1,237,350
kWh
$28,260
-
kW-mo/yr
- - -
02 2.4325: Upgrade conveyors $36,000 $40,966 - - - - $36,000
03 2.4156: Establish a preventative maintenance program $15,109 $12,480 $4,275
70,080
kWh
- $834 $10,000 -
TOTAL RECOMMENDED $154,847 $443,446 $79,753
1,307,430
kWh
$28,260
-
kW-mo/yr
$834 $10,000 $36,000
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs