Assessment Year | 2023 |
---|---|
Principal Product | Medical Instruments |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $50 M to 100M |
# of Employees | 336 |
Plant Area |
220,000
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $634,351 | 10,326,000 |
kWh
|
$0.061 | |
Electricity Demand | $273,837 | 18,651 |
kW-mo/yr
|
$14.68 | |
Electricity Fees | $183,625 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $36,243 | 5,511 |
Tgal
|
$6.58 | |
Water Disposal | $50,243 | 7,123 |
Tgal
|
$7.05 | |
TOTAL YEARLY COSTS | $1,178,299 | ||||
RECOMMENDED SAVINGS* | $261,046 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $38,905 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $172,404 | $974,914 |
$59,999
983,592
kWh
|
$112,405
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $31,739 | $1,660 |
$23,855
391,071
kWh
|
$7,884
-
kW-mo/yr
|
- | |
03 | 2.8114: Change rate schedules or other changes in utility service | $25,267 | - | - | - | $25,267 | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $16,344 | $70,840 |
$12,086
198,126
kWh
|
$4,258
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,166 | $12,997 |
$5,169
84,734
kWh
|
$1,997
-
kW-mo/yr
|
- | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,831 | $6,950 |
$3,480
57,042
kWh
|
$1,351
-
kW-mo/yr
|
- | |
07 | 2.9112: Use solar heat to heat water | $1,687 | $8,166 |
$1,687
27,655
kWh
|
- | - | |
08 | 2.2511: Insulate bare equipment | $1,608 | $1,012 |
$1,160
19,023
kWh
|
$448
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $261,046 | $1,076,539 |
$107,436
1,761,243
kWh
|
$128,343
-
kW-mo/yr
|
$25,267 | ||
TOTAL IMPLEMENTED | $38,905 | $14,657 |
$29,024
475,805
kWh
|
$9,881
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs