ITAC Assessment: MI0425
ITAC logo
ITAC Assessment: MI0425
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Ready-mixed Concrete
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $100
M
to 500
M
# of Employees 35
Plant Area 165,000
ft2
Annual Production 690,000
ton
Production Hrs. Annual 3,640
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,381 531,360
kWh
Electricity Demand $28,464 2,397
kW-mo/yr
Electricity Fees $16,466 -
Fuel Oil #2 $800,000 29,543
MMBtu
TOTAL YEARLY COSTS $879,311
RECOMMENDED SAVINGS* $32,515 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,350

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Ancillary Material Cost Savings
01 2.8226: Increase efficiency of trucks $15,746 $16,000 - - $11,996
-
MMBtu
$3,750
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,321 $5,505 $3,946
60,700
kWh
$2,375
-
kW-mo/yr
- -
03 2.6218: Turn off equipment when not in use $4,121 - $4,121
63,396
kWh
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,229 $1,980 $2,398
36,895
kWh
$831
-
kW-mo/yr
- -
05 2.4325: Upgrade conveyors $2,168 $4,160 $1,353
20,808
kWh
$815
-
kW-mo/yr
- -
06 2.4224: Upgrade controls on compressors $930 $280 $586
9,017
kWh
$344
-
kW-mo/yr
- -
TOTAL RECOMMENDED $32,515 $27,925 $12,404
190,816
kWh
$4,365
-
kW-mo/yr
$11,996
-
MMBtu
$3,750
TOTAL IMPLEMENTED $7,350 $1,980 $6,519
100,291
kWh
$831
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs