Assessment Year | 2023 |
---|---|
Principal Product | Ready-mixed Concrete |
NAICS | 327320: Ready-Mix Concrete Manufacturing |
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $100 M to 500M |
# of Employees | 35 |
Plant Area |
165,000
ft2
|
Annual Production | 690,000
ton
|
Production Hrs. Annual | 3,640
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $34,381 | 531,360 |
kWh
|
$0.065 |
Electricity Demand | $28,464 | 2,397 |
kW-mo/yr
|
$11.87 |
Electricity Fees | $16,466 | - |
|
- |
Fuel Oil #2 | $800,000 | 29,543 |
MMBtu
|
$27.08 |
TOTAL YEARLY COSTS | $879,311 | |||
RECOMMENDED SAVINGS* | $32,515 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,350 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8226: Increase efficiency of trucks | $15,746 | $16,000 | - | - |
$11,996
-
MMBtu
|
$3,750 | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,321 | $5,505 |
$3,946
60,700
kWh
|
$2,375
-
kW-mo/yr
|
- | - | |
03 | 2.6218: Turn off equipment when not in use | $4,121 | - |
$4,121
63,396
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,229 | $1,980 |
$2,398
36,895
kWh
|
$831
-
kW-mo/yr
|
- | - | |
05 | 2.4325: Upgrade conveyors | $2,168 | $4,160 |
$1,353
20,808
kWh
|
$815
-
kW-mo/yr
|
- | - | |
06 | 2.4224: Upgrade controls on compressors | $930 | $280 |
$586
9,017
kWh
|
$344
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $32,515 | $27,925 |
$12,404
190,816
kWh
|
$4,365
-
kW-mo/yr
|
$11,996
-
MMBtu
|
$3,750 | ||
TOTAL IMPLEMENTED | $7,350 | $1,980 |
$6,519
100,291
kWh
|
$831
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs