| Assessment Year | 2022 |
|---|---|
| Principal Product | Chemical and organic extracts |
| NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
| SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
125,000
ft2
|
| Annual Production | 9,800,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $238,130 | 4,824,554 |
kWh
|
$0.049 | |
| Electricity Demand | $64,778 | 6,643 |
kW-mo/yr
|
$9.75 | |
| Electricity Fees | $64,767 | - |
|
- | |
| Natural Gas | $43,107 | 11,053 |
MMBtu
|
$3.90 | |
| Waste Disposal Costs | |||||
| Water Usage | $25,753 | 5,941 |
Tgal
|
$4.33 | |
| Water Disposal | $32,438 | 5,941 |
Tgal
|
$5.46 | |
| TOTAL YEARLY COSTS | $468,973 | ||||
| RECOMMENDED SAVINGS* | $51,753 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $36,328 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $28,220 | $580 |
$22,165
452,343
kWh
|
$6,055
-
kW-mo/yr
|
- | - | |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,764 | $479 |
$7,404
151,093
kWh
|
$2,360
-
kW-mo/yr
|
- | - | |
| 03 | 3.4155: Meter waste water | $8,108 | $1,533 | - | - | - |
$8,108
-
Tgal
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,549 | $1,660 |
$1,652
33,723
kWh
|
$897
-
kW-mo/yr
|
- | - | |
| 05 | 2.1241: Reduce excessive boiler blowdown | $1,720 | $2,088 | - | - |
$978
-
MMBtu
|
$742
-
Tgal
|
|
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,392 | $2,520 | - | - |
$1,392
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $51,753 | $8,860 |
$31,221
637,159
kWh
|
$9,312
-
kW-mo/yr
|
$2,370
-
MMBtu
|
$8,850
-
Tgal
|
||
| TOTAL IMPLEMENTED | $36,328 | $2,113 |
$22,165
452,343
kWh
|
$6,055
-
kW-mo/yr
|
- |
$8,108
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs