Assessment Year | 2022 |
---|---|
Principal Product | Electroplating |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $5 M to 10M |
# of Employees | 84 |
Plant Area |
133,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $307,603 | 1,532,503 |
kWh
|
$0.20 |
Electricity Demand | $67,285 | 6,170 |
kW-mo/yr
|
$10.91 |
Electricity Fees | $3,479 | - |
|
- |
Fuel Oil #2 | $282,499 | 14,837 |
MMBtu
|
$19.04 |
TOTAL YEARLY COSTS | $660,866 | |||
RECOMMENDED SAVINGS* | $49,444 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $47,788 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $15,827 | $43,707 | - | - | $15,827 | - | |
02 | 2.4224: Upgrade controls on compressors | $11,648 | $5,536 |
$10,072
50,107
kWh
|
$1,576
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,718 | $2,020 |
$8,737
43,470
kWh
|
$981
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,275 | $5,780 |
$4,541
22,593
kWh
|
$734
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,149 | $40 |
$3,573
17,777
kWh
|
$576
-
kW-mo/yr
|
- | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,656 | $480 | - | - | - |
$1,656
-
MMBtu
|
|
07 | 2.6127: Maintain air filters by cleaning or replacement | $1,171 | $99 |
$1,007
5,011
kWh
|
$164
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $49,444 | $57,662 |
$27,930
138,958
kWh
|
$4,031
-
kW-mo/yr
|
$15,827 |
$1,656
-
MMBtu
|
||
TOTAL IMPLEMENTED | $47,788 | $57,182 |
$27,930
138,958
kWh
|
$4,031
-
kW-mo/yr
|
$15,827 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs