Assessment Year | 2022 |
---|---|
Principal Product | Metal Stamping and sheets |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
74,000
ft2
|
Annual Production | 60,000
pieces
|
Production Hrs. Annual | 5,772
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,669 | 957,600 |
kWh
|
$0.058 |
Electricity Demand | $37,278 | 3,210 |
kW-mo/yr
|
$11.61 |
Electricity Fees | $16,164 | - |
|
- |
TOTAL YEARLY COSTS | $109,111 | |||
RECOMMENDED SAVINGS* | $22,527 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,070 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,050 | $1,980 |
$4,273
73,671
kWh
|
$1,777
-
kW-mo/yr
|
|
02 | 2.7221: Lower temperature during the winter season and vice-versa | $3,776 | $580 |
$2,452
42,277
kWh
|
$1,324
-
kW-mo/yr
|
|
03 | 2.7425: Clean or color roof to reduce solar load | $3,485 | $12,386 |
$2,405
41,460
kWh
|
$1,080
-
kW-mo/yr
|
|
04 | 2.4239: Eliminate or reduce compressed air usage | $3,047 | $2,100 |
$2,153
37,125
kWh
|
$894
-
kW-mo/yr
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,039 | $5,244 |
$1,331
22,950
kWh
|
$708
-
kW-mo/yr
|
|
06 | 2.4239: Eliminate or reduce compressed air usage | $3,196 | $5,530 |
$2,255
38,887
kWh
|
$941
-
kW-mo/yr
|
|
07 | 2.4227: Use compressor air filters | $934 | $580 |
$597
10,297
kWh
|
$337
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $22,527 | $28,400 |
$15,466
266,667
kWh
|
$7,061
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $12,070 | $9,904 |
$8,354
144,043
kWh
|
$3,716
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs