Assessment Year | 2021 |
---|---|
Principal Product | Pharma Tablets |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 80 |
Plant Area |
50,000
ft2
|
Annual Production | 40,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $315,047 | 7,293,120 |
kWh
|
$0.043 | |
Electricity Demand | $177,413 | 13,010 |
kW-mo/yr
|
$13.64 | |
Electricity Fees | $86,142 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $14,093 | 3,001 |
Tgal
|
$4.70 | |
Water Disposal | $29,598 | 3,001 |
Tgal
|
$9.86 | |
TOTAL YEARLY COSTS | $622,293 | ||||
RECOMMENDED SAVINGS* | $54,033 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $23,870 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $17,603 | $2,100 |
$4,345
101,058
kWh
|
$13,258
-
kW-mo/yr
|
- | |
02 | 3.4116: Meter recycled water (to reduce sewer charges) | $14,790 | $1,380 | - | - |
$14,790
-
Tgal
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,523 | $1,980 |
$4,345
101,058
kWh
|
$3,178
-
kW-mo/yr
|
- | |
04 | 2.7425: Clean or color roof to reduce solar load | $6,816 | $15,328 |
$2,560
59,535
kWh
|
$4,256
-
kW-mo/yr
|
- | |
05 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $5,744 | $26,640 |
$3,275
76,167
kWh
|
$2,469
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $944 | $811 |
$658
15,297
kWh
|
$286
-
kW-mo/yr
|
- | |
07 | 2.7135: Install occupancy sensors | $613 | $255 |
$613
14,257
kWh
|
- | - | |
TOTAL RECOMMENDED | $54,033 | $48,494 |
$15,796
367,372
kWh
|
$23,447
-
kW-mo/yr
|
$14,790
-
Tgal
|
||
TOTAL IMPLEMENTED | $23,870 | $4,426 |
$5,616
130,612
kWh
|
$3,464
-
kW-mo/yr
|
$14,790
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs