Assessment Year | 2021 |
---|---|
Principal Product | Landing Gear/ Aircraft |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 192 |
Plant Area |
100,000
ft2
|
Annual Production | 1,200
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $280,621 | 6,943,183 |
kWh
|
$0.040 | |
Electricity Demand | $219,647 | 13,106 |
kW-mo/yr
|
$16.76 | |
Electricity Fees | $85,160 | - |
|
- | |
Natural Gas | $3,073 | 230 |
MMBtu
|
$13.36 | |
Waste Disposal Costs | |||||
Water Usage | $25,691 | 1,653 |
Tgal
|
$15.54 | |
Water Disposal | $19,038 | 1,653 |
Tgal
|
$11.52 | |
TOTAL YEARLY COSTS | $633,230 | ||||
RECOMMENDED SAVINGS* | $58,900 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $28,257 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $24,463 | $480 |
$15,463
386,564
kWh
|
$9,000
-
kW-mo/yr
|
- | - | - | |
02 | 3.4116: Meter recycled water (to reduce sewer charges) | $12,537 | $1,380 | - | - | - | - |
$12,537
-
Tgal
|
|
03 | 2.8114: Change rate schedules or other changes in utility service | $9,170 | $2,549 | - | - | $9,170 | - | - | |
04 | 2.7425: Clean or color roof to reduce solar load | $4,060 | $14,609 |
$2,250
56,249
kWh
|
$1,810
-
kW-mo/yr
|
- | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $2,836 | $2,100 |
$2,580
64,496
kWh
|
$256
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,427 | $1,980 |
$1,539
38,466
kWh
|
$888
-
kW-mo/yr
|
- | - | - | |
07 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $2,040 | $616 |
$695
17,370
kWh
|
$553
-
kW-mo/yr
|
- |
$792
-
MMBtu
|
- | |
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,367 | $2,549 |
$747
18,682
kWh
|
$620
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $58,900 | $26,263 |
$23,274
581,827
kWh
|
$13,127
-
kW-mo/yr
|
$9,170 |
$792
-
MMBtu
|
$12,537
-
Tgal
|
||
TOTAL IMPLEMENTED | $28,257 | $5,009 |
$17,749
443,712
kWh
|
$10,508
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs