Assessment Year | 2021 |
---|---|
Principal Product | Aerospace Engines |
NAICS | 336412: Aircraft Engine and Engine Parts Manufacturing |
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $50 M to 100M |
# of Employees | 100 |
Plant Area |
35,000
ft2
|
Annual Production | 20,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $95,063 | 2,052,720 |
kWh
|
$0.046 | |
Electricity Demand | $70,399 | 5,936 |
kW-mo/yr
|
$11.86 | |
Electricity Fees | $16,357 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $9,081 | 1,460 |
Tgal
|
$6.22 | |
Water Disposal | $10,439 | 1,460 |
Tgal
|
$7.15 | |
TOTAL YEARLY COSTS | $201,339 | ||||
RECOMMENDED SAVINGS* | $31,237 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $3,242 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,223 | $3,645 |
$6,815
148,159
kWh
|
$2,408
-
kW-mo/yr
|
- | |
02 | 2.9112: Use solar heat to heat water | $7,209 | $8,409 |
$4,647
101,018
kWh
|
$2,562
-
kW-mo/yr
|
- | |
03 | 2.4112: Install soft-start to eliminate nuisance trips | $5,430 | $2,740 |
$1,872
40,697
kWh
|
$3,558
-
kW-mo/yr
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $4,045 | $1,796 |
$2,989
64,976
kWh
|
$1,056
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,278 | $3,204 |
$1,519
33,022
kWh
|
$759
-
kW-mo/yr
|
- | |
06 | 3.4116: Meter recycled water (to reduce sewer charges) | $2,088 | $1,306 | - | - |
$2,088
-
Tgal
|
|
07 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $964 | $1,884 |
$964
20,966
kWh
|
- | - | |
TOTAL RECOMMENDED | $31,237 | $22,984 |
$18,806
408,838
kWh
|
$10,343
-
kW-mo/yr
|
$2,088
-
Tgal
|
||
TOTAL IMPLEMENTED | $3,242 | $5,088 |
$2,483
53,988
kWh
|
$759
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs