Assessment Year | 2021 |
---|---|
Principal Product | Sheet Metal Cabinets |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
140,000
ft2
|
Annual Production | 25,000
pieces
|
Production Hrs. Annual | 4,355
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $100,236 | 2,042,775 |
kWh
|
$0.049 |
Electricity Demand | $57,731 | 5,159 |
kW-mo/yr
|
$11.19 |
Electricity Fees | $27,215 | - |
|
- |
TOTAL YEARLY COSTS | $185,182 | |||
RECOMMENDED SAVINGS* | $48,086 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,670 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $12,828 | $480 |
$9,818
200,367
kWh
|
$3,010
-
kW-mo/yr
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,840 | $2,673 |
$5,971
121,852
kWh
|
$1,869
-
kW-mo/yr
|
|
03 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $7,580 | $6,182 |
$4,973
101,496
kWh
|
$2,607
-
kW-mo/yr
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,737 | $11,160 |
$4,135
84,383
kWh
|
$2,602
-
kW-mo/yr
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,502 | $2,100 |
$3,173
64,754
kWh
|
$1,329
-
kW-mo/yr
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,909 | $1,980 |
$2,756
56,254
kWh
|
$1,153
-
kW-mo/yr
|
|
07 | 2.6127: Maintain air filters by cleaning or replacement | $1,694 | $1,195 |
$1,179
24,066
kWh
|
$515
-
kW-mo/yr
|
|
08 | 2.7135: Install occupancy sensors | $1,344 | $1,042 |
$1,344
27,437
kWh
|
- | |
09 | 2.7134: Use photocell controls | $981 | $1,141 |
$533
10,870
kWh
|
$448
-
kW-mo/yr
|
|
10 | 2.2522: Isolate hot or cold equipment | $671 | $560 |
$514
10,489
kWh
|
$157
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $48,086 | $28,513 |
$34,396
701,968
kWh
|
$13,690
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $29,670 | $16,915 |
$21,061
429,824
kWh
|
$8,609
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs