Assessment Year | 2019 |
---|---|
Principal Product | Nutrition Products |
NAICS | 325411: Medicinal and Botanical Manufacturing |
SIC | 2833: Medicinal Chemicals and Botanical Products |
Sales Range | $50 M to 100M |
# of Employees | 65 |
Plant Area |
74,000
ft2
|
Annual Production | 4,500,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $107,536 | 2,412,480 |
kWh
|
$0.045 |
Electricity Demand | $79,097 | 5,928 |
kW-mo/yr
|
$13.34 |
Electricity Fees | $50,098 | - |
|
- |
Natural Gas | $22,434 | 1,422 |
MMBtu
|
$15.78 |
TOTAL YEARLY COSTS | $259,165 | |||
RECOMMENDED SAVINGS* | $101,167 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $95,484 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $38,687 | $109,552 |
$27,492
610,939
kWh
|
$11,195
-
kW-mo/yr
|
|
02 | 2.7425: Clean or color roof to reduce solar load | $21,750 | $35,446 |
$6,512
144,711
kWh
|
$15,238
-
kW-mo/yr
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,252 | $23,997 |
$11,193
248,732
kWh
|
$8,059
-
kW-mo/yr
|
|
04 | 2.6218: Turn off equipment when not in use | $10,631 | $3,600 |
$10,631
236,255
kWh
|
- | |
05 | 2.7229: Air condition only space necessary | $5,164 | $16,940 |
$3,670
81,549
kWh
|
$1,494
-
kW-mo/yr
|
|
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,784 | $7,500 |
$2,410
53,557
kWh
|
$1,374
-
kW-mo/yr
|
|
07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,899 | $3,316 |
$1,352
30,035
kWh
|
$547
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $101,167 | $200,351 |
$63,260
1,405,778
kWh
|
$37,907
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $95,484 | $189,535 |
$59,498
1,322,186
kWh
|
$35,986
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs