| Assessment Year | 2019 |
|---|---|
| Principal Product | Treatede Water |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
2,150,000
ft2
|
| Annual Production | 120,000
Tgal
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,703,658 | 45,844,800 |
kWh
|
$0.037 | |
| Electricity Demand | $695,082 | 79,658 |
kW-mo/yr
|
$8.73 | |
| Electricity Fees | $233,912 | - |
|
- | |
| Fuel Oil #2 | $204,399 | 12,366 |
MMBtu
|
$16.53 | |
| Waste Disposal Costs | |||||
| Water Usage | $297,500 | 35,000 |
Tgal
|
$8.50 | |
| TOTAL YEARLY COSTS | $3,134,551 | ||||
| RECOMMENDED SAVINGS* | $1,634,954 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $1,549,415 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $713,110 | $8,242,656 |
$1,696,258
45,844,800
kWh
|
$695,096
-
kW-mo/yr
|
$204,399
-
MMBtu
|
- | $(-1,882,643.0) | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $478,275 | $6,028,646 |
$339,252
9,168,960
kWh
|
$139,023
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $270,674 | $806,400 |
$204,444
5,525,520
kWh
|
$66,230
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.7313: Eliminate oxygen loss | $85,219 | $51,000 |
$64,364
1,739,556
kWh
|
$20,855
-
kW-mo/yr
|
- | - | - | |
| 05 | 3.4151: Minimize water usage | $77,140 | $207,600 |
$(-318.0)
(-8,596)
kWh
|
$(-105.0)
-
kW-mo/yr
|
- |
$77,563
-
Tgal
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,962 | $18,807 |
$6,016
162,594
kWh
|
$1,946
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7221: Lower temperature during the winter season and vice-versa | $2,254 | $480 |
$1,757
47,481
kWh
|
$497
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.7425: Clean or color roof to reduce solar load | $320 | $1,549 |
$242
6,507
kWh
|
$78
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $1,634,954 | $15,357,138 |
$2,312,015
62,486,822
kWh
|
$923,620
-
kW-mo/yr
|
$204,399
-
MMBtu
|
$77,563
-
Tgal
|
$(-1,882,643.0) | ||
| TOTAL IMPLEMENTED | $1,549,415 | $15,304,589 |
$2,247,409
60,740,759
kWh
|
$902,687
-
kW-mo/yr
|
$204,399
-
MMBtu
|
$77,563
-
Tgal
|
$(-1,882,643.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs