ITAC Assessment: LT0118
ITAC logo
ITAC Assessment: LT0118
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product FEED PELLETS & CHICKS
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area
n/a
Annual Production 125,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,966 2,927,902
kWh
Natural Gas $60,578 18,639
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,202 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $860 $600 - $860
-
MMBtu
-
02 2.1131: Repair faulty insulation in furnaces, boilers, etc $430 $400 - $430
-
MMBtu
-
03 2.4133: Use most efficient type of electric motors $1,000 $1,900 $1,000
24,033
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,240 - $1,240
42,497
kWh
- -
05 2.7221: Lower temperature during the winter season and vice-versa $194 $450 $194
10,844
kWh
- -
06 2.7441: Replace broken windows and/or window sash $1,363 $200 $1,363
46,893
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $115 $92 $125
2,638
kWh
- $(-10.0)
TOTAL RECOMMENDED $5,202 $3,642 $3,922
126,905
kWh
$1,290
-
MMBtu
$(-10.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs