| Assessment Year | 2019 |
|---|---|
| Principal Product | Bean Sprout |
| NAICS | 311999: All Other Miscellaneous Food Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 50 |
| Plant Area |
45,000
ft2
|
| Annual Production | 2,600,000
lb
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $51,826 | 995,827 |
kWh
|
$0.052 |
| Electricity Demand | $25,491 | 2,372 |
kW-mo/yr
|
$10.75 |
| Electricity Fees | $17,854 | - |
|
- |
| Fuel Oil #2 | $33,931 | 1,647 |
MMBtu
|
$20.60 |
| TOTAL YEARLY COSTS | $129,102 | |||
| RECOMMENDED SAVINGS* | $81,127 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,108 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3113: Make ice during off peak hours for cooling | $33,896 | $289,880 | - |
$20,430
-
kW-mo/yr
|
- | - | $13,466 | - | |
| 02 | 2.7442: Keep doors and windows shut when not on use | $14,613 | $8,320 |
$11,389
219,016
kWh
|
$3,224
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 4.122: Develop standard procedures to improve internal yields | $10,140 | $8,840 | - | - | - | - | - | $10,140 | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $10,108 | $3,480 |
$4,906
94,337
kWh
|
$5,202
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.2628: Utilize a less expensive cooling method | $7,147 | $40,000 |
$(-2,988.0)
(-57,460)
kWh
|
- | - |
$10,135
-
MMBtu
|
- | - | |
| 06 | 2.8226: Increase efficiency of trucks | $3,675 | $4,060 | - | - | - | - | $3,675 | - | |
| 07 | 2.8112: Combine utility meters | $730 | $240 | - | - | $730 | - | - | - | |
| 08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $510 | $165 |
$397
7,643
kWh
|
$113
-
kW-mo/yr
|
- | - | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $308 | $395 |
$308
5,932
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $81,127 | $355,380 |
$14,012
269,468
kWh
|
$28,969
-
kW-mo/yr
|
$730 |
$10,135
-
MMBtu
|
$17,141 | $10,140 | ||
| TOTAL IMPLEMENTED | $33,108 | $52,205 |
$13,704
263,536
kWh
|
$8,539
-
kW-mo/yr
|
$730 |
$10,135
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs