Assessment Year | 2018 |
---|---|
Principal Product | Pharmaceuticals |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 360 |
Plant Area |
236,000
ft2
|
Annual Production | 2,600,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,528,881 | 21,357,534 |
kWh
|
$0.17 |
Electricity Demand | $302,032 | 39,225 |
kW-mo/yr
|
$7.70 |
Electricity Fees | $5,400 | - |
|
- |
Natural Gas | $262,800 | 21,900 |
MMBtu
|
$12.00 |
TOTAL YEARLY COSTS | $4,099,113 | |||
RECOMMENDED SAVINGS* | $1,974,187 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,353,527 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $1,225,133 | $10,935,180 |
$854,853
5,180,927
kWh
|
$54,647
-
kW-mo/yr
|
$315,633 | |
02 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $279,023 | $250,000 |
$262,260
1,589,460
kWh
|
$16,763
-
kW-mo/yr
|
- | |
03 | 2.6218: Turn off equipment when not in use | $254,041 | $3,280 |
$254,041
1,539,641
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $95,116 | $69,861 |
$86,300
523,030
kWh
|
$8,816
-
kW-mo/yr
|
- | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $47,520 | $480 |
$44,663
270,684
kWh
|
$2,857
-
kW-mo/yr
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $33,278 | $2,030 |
$31,278
189,564
kWh
|
$2,000
-
kW-mo/yr
|
- | |
07 | 2.3212: Optimize plant power factor | $28,281 | $41,300 | - |
$28,281
-
kW-mo/yr
|
- | |
08 | 2.7135: Install occupancy sensors | $11,795 | $9,000 |
$10,609
64,297
kWh
|
$1,186
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $1,974,187 | $11,311,131 |
$1,544,004
9,357,603
kWh
|
$114,550
-
kW-mo/yr
|
$315,633 | ||
TOTAL IMPLEMENTED | $1,353,527 | $11,007,071 |
$972,431
5,893,521
kWh
|
$65,463
-
kW-mo/yr
|
$315,633 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs