Assessment Year | 2018 |
---|---|
Principal Product | Surgical Medical Devices |
NAICS | 622110: General Medical and Surgical Hospitals |
SIC | 8062: General Medical and Surgical Hospitals |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
38,550
ft2
|
Annual Production | 12,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $138,955 | 764,666 |
kWh
|
$0.18 |
Electricity Demand | $19,142 | 2,486 |
kW-mo/yr
|
$7.70 |
Electricity Fees | $5,400 | - |
|
- |
TOTAL YEARLY COSTS | $163,497 | |||
RECOMMENDED SAVINGS* | $67,055 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $22,077 | $3,280 |
$22,077
121,303
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,126 | $12,487 |
$14,356
78,880
kWh
|
$770
-
kW-mo/yr
|
|
03 | 2.7425: Clean or color roof to reduce solar load | $13,231 | $10,979 |
$11,257
61,849
kWh
|
$1,974
-
kW-mo/yr
|
|
04 | 2.9111: Use solar heat to heat make-up air | $7,395 | $10,000 |
$6,995
38,434
kWh
|
$400
-
kW-mo/yr
|
|
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,623 | $12,700 |
$3,423
18,807
kWh
|
$200
-
kW-mo/yr
|
|
06 | 2.7135: Install occupancy sensors | $3,272 | $2,295 |
$3,087
16,964
kWh
|
$185
-
kW-mo/yr
|
|
07 | 2.3212: Optimize plant power factor | $1,201 | $3,628 | - |
$1,201
-
kW-mo/yr
|
|
08 | 2.7134: Use photocell controls | $1,130 | $1,376 |
$876
4,812
kWh
|
$254
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $67,055 | $56,745 |
$62,071
341,049
kWh
|
$4,984
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs