Assessment Year | 2018 |
---|---|
Principal Product | Surgical Medical Devices |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
220,000
ft2
|
Annual Production | 250,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $591,008 | 10,745,600 |
kWh
|
$0.055 |
Electricity Demand | $171,939 | 20,228 |
kW-mo/yr
|
$8.50 |
Electricity Fees | $140,560 | - |
|
- |
TOTAL YEARLY COSTS | $903,508 | |||
RECOMMENDED SAVINGS* | $232,252 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $150,260 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $45,349 | $76,979 |
$35,956
653,737
kWh
|
$9,393
-
kW-mo/yr
|
|
02 | 2.7221: Lower temperature during the winter season and vice-versa | $41,184 | $480 |
$32,752
595,496
kWh
|
$8,432
-
kW-mo/yr
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $31,197 | $11,846 |
$24,805
451,000
kWh
|
$6,392
-
kW-mo/yr
|
|
04 | 2.2511: Insulate bare equipment | $26,104 | $3,000 |
$20,757
377,405
kWh
|
$5,347
-
kW-mo/yr
|
|
05 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $24,458 | $31,600 |
$20,182
366,939
kWh
|
$4,276
-
kW-mo/yr
|
|
06 | 2.7425: Clean or color roof to reduce solar load | $21,780 | $78,320 |
$9,680
176,000
kWh
|
$12,100
-
kW-mo/yr
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,813 | $2,030 |
$13,042
237,121
kWh
|
$2,771
-
kW-mo/yr
|
|
08 | 2.7135: Install occupancy sensors | $14,515 | $19,215 |
$11,540
209,813
kWh
|
$2,975
-
kW-mo/yr
|
|
09 | 2.7111: Reduce illumination to minimum necessary levels | $4,557 | $2,528 |
$3,460
62,915
kWh
|
$1,097
-
kW-mo/yr
|
|
10 | 2.4323: Use optimum size and capacity equipment | $3,724 | $7,314 |
$3,069
55,808
kWh
|
$655
-
kW-mo/yr
|
|
11 | 2.4239: Eliminate or reduce compressed air usage | $3,571 | $6,578 |
$2,355
42,814
kWh
|
$1,216
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $232,252 | $239,890 |
$177,598
3,229,048
kWh
|
$54,654
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $150,260 | $115,596 |
$119,471
2,172,194
kWh
|
$30,789
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs