ITAC Assessment: MI0320
ITAC logo
ITAC Assessment: MI0320
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Electrical Terminals
NAICS 335931: Current-Carrying Wiring Device Manufacturing
SIC 3643: Current-Carrying Wiring Devices
Sales Range $50
M
to 100
M
# of Employees 157
Plant Area 45,000
ft2
Annual Production 1,500,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Puerto Rico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $409,913 2,743,118
kWh
Electricity Demand $79,453 8,172
kW-mo/yr
Electricity Fees $8,126 -
TOTAL YEARLY COSTS $497,492
RECOMMENDED SAVINGS* $266,229 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $194,732

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.2628: Utilize a less expensive cooling method $58,668 $31,800 $47,860
321,205
kWh
$6,008
-
kW-mo/yr
$4,800
02 2.7221: Lower temperature during the winter season and vice-versa $58,406 $120 $51,896
348,295
kWh
$6,510
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $53,871 $1,660 $46,959
315,164
kWh
$6,912
-
kW-mo/yr
-
04 2.7425: Clean or color roof to reduce solar load $40,560 $27,600 $36,039
241,872
kWh
$4,521
-
kW-mo/yr
-
05 2.6218: Turn off equipment when not in use $23,860 $3,600 $23,860
160,136
kWh
- -
06 2.3212: Optimize plant power factor $18,035 $23,565 - $18,035
-
kW-mo/yr
-
07 2.4239: Eliminate or reduce compressed air usage $7,588 $2,300 $6,742
45,250
kWh
$846
-
kW-mo/yr
-
08 2.7245: Use direct air supply to exhaust hoods $3,716 $6,530 $3,302
22,159
kWh
$414
-
kW-mo/yr
-
09 2.7447: Install vinyl strip / high speed / air curtain doors $1,100 $2,272 $978
6,562
kWh
$122
-
kW-mo/yr
-
10 2.2511: Insulate bare equipment $425 $134 $328
2,199
kWh
$97
-
kW-mo/yr
-
TOTAL RECOMMENDED $266,229 $99,581 $217,964
1,462,842
kWh
$43,465
-
kW-mo/yr
$4,800
TOTAL IMPLEMENTED $194,732 $56,545 $158,754
1,065,467
kWh
$35,978
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs