ITAC Assessment: MS0113
ITAC logo
ITAC Assessment: MS0113
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Battery Components
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 150,000
ft2
Annual Production 12,500,000
lb
Production Hrs. Annual 7,344
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $512,246 16,691,970
kWh
Electricity Demand $298,526 32,172
kW-mo/yr
Electricity Fees $14,476 -
Natural Gas $43,357 8,226
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $110,363 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,432

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,208 $9,250 $6,244
204,865
kWh
$3,813
-
kW-mo/yr
$151 - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,045 $8,030 $3,986
130,715
kWh
- $59 - -
03 2.2612: Use cooling tower water instead of refrigeration $10,852 $7,236 $10,692
350,821
kWh
- $160 - -
04 2.3212: Optimize plant power factor $11,323 $4,875 - - $11,323 - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $70,934 $513,675 $67,021
2,198,124
kWh
$2,864
-
kW-mo/yr
$1,049 - -
06 3.1191: Change procedures / equipment / operating conditions $1,049 $1,235 - - - - $1,049
07 3.6124: Burn waste oil for heat $1,952 $2,745 $1,430
46,893
kWh
- $22 $500
-
gal
-
TOTAL RECOMMENDED $110,363 $547,046 $89,373
2,931,418
kWh
$6,677
-
kW-mo/yr
$12,764 $500
-
gal
$1,049
TOTAL IMPLEMENTED $33,432 $22,596 $16,936
555,686
kWh
$3,813
-
kW-mo/yr
$11,634 - $1,049
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs