Assessment Year | 2017 |
---|---|
Principal Product | Biscuit Foodsd |
NAICS | 311211: Flour Milling |
SIC | 2041: Flour and Other Grain Mill Products |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
89,407
ft2
|
Annual Production | 65,000
lb
|
Production Hrs. Annual | 4,208
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $461,718 | 3,081,434 |
kWh
|
$0.15 |
Electricity Demand | $68,136 | 6,990 |
kW-mo/yr
|
$9.75 |
Electricity Fees | $6,318 | - |
|
- |
TOTAL YEARLY COSTS | $536,172 | |||
RECOMMENDED SAVINGS* | $150,223 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $127,608 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $60,626 | $3,600 |
$60,626
404,170
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,550 | $39,636 |
$27,327
182,182
kWh
|
$5,223
-
kW-mo/yr
|
- | |
03 | 2.2511: Insulate bare equipment | $21,088 | $106,884 |
$16,570
110,467
kWh
|
$4,518
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,714 | $1,660 |
$11,701
78,011
kWh
|
$1,013
-
kW-mo/yr
|
- | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $8,034 | $9,660 |
$7,361
49,072
kWh
|
$673
-
kW-mo/yr
|
- | |
06 | 2.4239: Eliminate or reduce compressed air usage | $4,318 | $3,540 |
$3,626
24,173
kWh
|
$692
-
kW-mo/yr
|
- | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,294 | $100 | - | - | $4,294 | |
08 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,591 | $4,940 |
$3,015
20,098
kWh
|
$576
-
kW-mo/yr
|
- | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,527 | $3,864 |
$1,283
8,556
kWh
|
$244
-
kW-mo/yr
|
- | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,481 | $1,469 |
$1,481
9,872
kWh
|
- | - | |
TOTAL RECOMMENDED | $150,223 | $175,353 |
$132,990
886,601
kWh
|
$12,939
-
kW-mo/yr
|
$4,294 | ||
TOTAL IMPLEMENTED | $127,608 | $64,605 |
$115,137
767,578
kWh
|
$8,177
-
kW-mo/yr
|
$4,294 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs