Assessment Year | 2016 |
---|---|
Principal Product | Power Turbines |
NAICS | 333611: Turbine and Turbine Generator Set Units Manufacturing |
SIC | 3511: Steam, Gas, and Hydraulic Turbines, and Turbine Generator Set Units |
Sales Range | $100 M to 500M |
# of Employees | 439 |
Plant Area |
150,030
ft2
|
Annual Production | 21,018
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,103,566 | 18,381,934 |
kWh
|
$0.060 |
Electricity Demand | $400,942 | 41,927 |
kW-mo/yr
|
$9.56 |
Electricity Fees | $45,627 | - |
|
- |
TOTAL YEARLY COSTS | $1,550,135 | |||
RECOMMENDED SAVINGS* | $153,720 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $120,784 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $48,914 | $119,809 |
$38,298
638,296
kWh
|
$10,616
-
kW-mo/yr
|
- | |
02 | 2.7425: Clean or color roof to reduce solar load | $30,447 | $53,372 |
$21,175
352,927
kWh
|
$9,272
-
kW-mo/yr
|
- | |
03 | 2.2628: Utilize a less expensive cooling method | $16,987 | $25,335 |
$9,316
155,272
kWh
|
$2,031
-
kW-mo/yr
|
$5,640 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,015 | $1,700 |
$7,470
124,489
kWh
|
$4,545
-
kW-mo/yr
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,470 | $43,770 |
$9,411
156,859
kWh
|
$2,059
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,388 | $8,320 |
$9,343
155,716
kWh
|
$2,045
-
kW-mo/yr
|
- | |
07 | 2.4323: Use optimum size and capacity equipment | $6,723 | $4,691 |
$6,369
106,148
kWh
|
$354
-
kW-mo/yr
|
- | |
08 | 2.4239: Eliminate or reduce compressed air usage | $4,720 | $2,320 |
$3,917
65,276
kWh
|
$803
-
kW-mo/yr
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,968 | $7,680 |
$2,968
49,463
kWh
|
- | - | |
10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,936 | $2,430 |
$2,042
34,030
kWh
|
$894
-
kW-mo/yr
|
- | |
11 | 2.7135: Install occupancy sensors | $1,803 | $662 |
$1,803
30,052
kWh
|
- | - | |
12 | 2.4112: Install soft-start to eliminate nuisance trips | $1,779 | $3,350 |
$954
15,897
kWh
|
$825
-
kW-mo/yr
|
- | |
13 | 2.7134: Use photocell controls | $1,570 | $1,120 |
$1,570
26,166
kWh
|
- | - | |
TOTAL RECOMMENDED | $153,720 | $274,559 |
$114,636
1,910,591
kWh
|
$33,444
-
kW-mo/yr
|
$5,640 | ||
TOTAL IMPLEMENTED | $120,784 | $238,663 |
$91,422
1,523,699
kWh
|
$29,362
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs