ITAC Assessment: MA0625
ITAC logo
ITAC Assessment: MA0625
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Isostatic pressing of metal parts
NAICS 332811: Metal Heat Treating
SIC 3398: Metal Heat Treating
Sales Range $10
M
to 50
M
# of Employees 71
Plant Area 80,000
ft2
Annual Production 2,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $991,243 8,910,800
kWh
Electricity Demand $162,515 35,208
kW-mo/yr
Electricity Fees $838 -
Natural Gas $38,748 2,426
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,104 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,899

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $17,463 $31,000 $16,585
138,210
kWh
$878
-
kW-mo/yr
-
02 2.4131: Size electric motors for peak operating efficiency $8,935 $8,000 $8,935
74,460
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,861 $14,400 $7,468
62,230
kWh
$393
-
kW-mo/yr
-
04 2.6218: Turn off equipment when not in use $5,881 - $5,881
49,012
kWh
- -
05 2.7243: Improve air circulation with destratification fans / other methods $3,964 $10,530 $(-779.0)
(-6,490)
kWh
- $4,743
-
MMBtu
TOTAL RECOMMENDED $44,104 $63,930 $38,090
317,422
kWh
$1,271
-
kW-mo/yr
$4,743
-
MMBtu
TOTAL IMPLEMENTED $12,899 $18,530 $8,156
67,970
kWh
- $4,743
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs