ITAC Assessment: MI0301
ITAC logo
ITAC Assessment: MI0301
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Emergency Position Indicating Radio Beacons
NAICS 334220: Radio and Television Broadcasting and Wireless Communications Equipment Manufacturing
SIC 3663: Radio and Television Broadcasting and Communications Equipment
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 55,000
ft2
Annual Production 60,000,000
units
Production Hrs. Annual 4,420
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $77,761 1,539,720
kWh
Electricity Demand $35,323 3,376
kW-mo/yr
Electricity Fees $20,353 -
TOTAL YEARLY COSTS $133,437
RECOMMENDED SAVINGS* $53,060 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,070

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.3192: Use fossil fuel powered generator during peak demand periods $15,850 $1,120 $326
6,400
kWh
- $15,524
02 2.7142: Utilize higher efficiency lamps and/or ballasts $11,990 $35,099 $5,843
114,563
kWh
$6,147
-
kW-mo/yr
-
03 2.7447: Install vinyl strip / high speed / air curtain doors $7,246 $2,379 $4,654
91,251
kWh
$2,592
-
kW-mo/yr
-
04 2.7425: Clean or color roof to reduce solar load $6,075 $18,626 $3,902
76,505
kWh
$2,173
-
kW-mo/yr
-
05 2.6218: Turn off equipment when not in use $3,096 $322 $3,096
60,708
kWh
- -
06 2.2515: Use optimum thickness insulation $2,946 $2,710 $2,297
45,048
kWh
$649
-
kW-mo/yr
-
07 2.2437: Recover waste heat from equipment $2,197 $2,146 $1,716
33,641
kWh
$481
-
kW-mo/yr
-
08 2.7292: Lower ceiling to reduce conditioned space $1,288 $8,881 $828
16,238
kWh
$460
-
kW-mo/yr
-
09 2.7135: Install occupancy sensors $1,252 $2,200 $1,252
24,557
kWh
- -
10 2.7496: Install partitions to reduce size of conditioned space $580 $3,880 $580
11,367
kWh
- -
11 2.8114: Change rate schedules or other changes in utility service $540 $280 - - $540
TOTAL RECOMMENDED $53,060 $77,643 $24,494
480,278
kWh
$12,502
-
kW-mo/yr
$16,064
TOTAL IMPLEMENTED $15,070 $46,460 $7,923
155,358
kWh
$6,607
-
kW-mo/yr
$540
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs