ITAC Assessment: CO0072
ITAC logo
ITAC Assessment: CO0072
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product WHEAT FLOUR & BRAN
NAICS
n/a
SIC 2041: Flour and Other Grain Mill Products
Sales Range $10
M
to 50
M
# of Employees 23
Plant Area
n/a
Annual Production 141,200
ton
Production Hrs. Annual 8,472
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $377,376 7,613,130
kWh
Natural Gas $28,701 5,992
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $80,616 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,810

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4322: Use or replace with energy efficient substitutes $27,672 $75,000 $27,672
701,641
kWh
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $13,585 $13,500 $13,585
274,326
kWh
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,255 $20 $2,255
45,428
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $1,044 $200 $1,044
21,102
kWh
-
05 2.4312: Improve lubrication practices $17,594 - $17,594
355,217
kWh
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,883 $500 $1,883
38,101
kWh
-
07 2.2437: Recover waste heat from equipment $4,157 $5,000 $(-998.0)
(-20,223)
kWh
$5,155
-
MMBtu
08 2.7142: Utilize higher efficiency lamps and/or ballasts $12,426 $32,254 $12,426
250,879
kWh
-
TOTAL RECOMMENDED $80,616 $126,474 $75,461
1,666,471
kWh
$5,155
-
MMBtu
TOTAL IMPLEMENTED $31,810 $75,520 $31,810
785,170
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs