ITAC Assessment: MI0293
ITAC logo
ITAC Assessment: MI0293
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Wires
NAICS 331420: Copper Rolling, Drawing, Extruding, and Alloying
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area 33,000
ft2
Annual Production 100,000,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,436 1,434,480
kWh
Electricity Demand $37,284 3,514
kW-mo/yr
Electricity Fees $4,086 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,139 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,110

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7135: Install occupancy sensors $6,347 $1,120 $6,347
119,746
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,469 $6,560 $3,949
74,506
kWh
$1,520
-
kW-mo/yr
03 2.7425: Clean or color roof to reduce solar load $4,663 $8,284 $3,644
68,749
kWh
$1,019
-
kW-mo/yr
04 2.7496: Install partitions to reduce size of conditioned space $4,417 $8,450 $4,417
83,342
kWh
-
05 2.6218: Turn off equipment when not in use $3,266 $3,600 $3,266
61,623
kWh
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,795 $8,400 $2,190
41,319
kWh
$605
-
kW-mo/yr
07 2.7111: Reduce illumination to minimum necessary levels $2,436 $760 $1,759
33,197
kWh
$677
-
kW-mo/yr
08 2.7221: Lower temperature during the winter season and vice-versa $2,349 $40 $1,840
34,726
kWh
$509
-
kW-mo/yr
09 2.2515: Use optimum thickness insulation $2,315 $320 $1,668
31,469
kWh
$647
-
kW-mo/yr
10 2.4231: Reduce the pressure of compressed air to the minimum required $1,965 $40 $1,286
24,259
kWh
$679
-
kW-mo/yr
11 2.4323: Use optimum size and capacity equipment $1,742 $4,691 $1,371
25,865
kWh
$371
-
kW-mo/yr
12 2.4239: Eliminate or reduce compressed air usage $1,627 $1,480 $1,245
23,499
kWh
$382
-
kW-mo/yr
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,603 $1,660 $1,285
24,254
kWh
$318
-
kW-mo/yr
14 2.7142: Utilize higher efficiency lamps and/or ballasts $744 $2,400 $744
14,040
kWh
-
15 2.7447: Install vinyl strip / high speed / air curtain doors $286 $605 $222
4,197
kWh
$64
-
kW-mo/yr
16 2.7111: Reduce illumination to minimum necessary levels $115 $320 $83
1,572
kWh
$32
-
kW-mo/yr
TOTAL RECOMMENDED $42,139 $48,730 $35,316
666,363
kWh
$6,823
-
kW-mo/yr
TOTAL IMPLEMENTED $22,110 $28,584 $17,460
329,436
kWh
$4,650
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs