| Assessment Year | 2016 |
|---|---|
| Principal Product | Wires |
| NAICS | 331420: Copper Rolling, Drawing, Extruding, and Alloying |
| SIC | 3357: Drawing and Insulating of Nonferrous Wire |
| Sales Range | $10 M to 50M |
| # of Employees | 65 |
| Plant Area |
33,000
ft2
|
| Annual Production | 100,000,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $75,436 | 1,434,480 |
kWh
|
$0.053 |
| Electricity Demand | $37,284 | 3,514 |
kW-mo/yr
|
$10.61 |
| Electricity Fees | $4,086 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $42,139 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,110 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $6,347 | $1,120 |
$6,347
119,746
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,469 | $6,560 |
$3,949
74,506
kWh
|
$1,520
-
kW-mo/yr
|
|
| 03 | 2.7425: Clean or color roof to reduce solar load | $4,663 | $8,284 |
$3,644
68,749
kWh
|
$1,019
-
kW-mo/yr
|
|
| 04 | 2.7496: Install partitions to reduce size of conditioned space | $4,417 | $8,450 |
$4,417
83,342
kWh
|
- | |
| 05 | 2.6218: Turn off equipment when not in use | $3,266 | $3,600 |
$3,266
61,623
kWh
|
- | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,795 | $8,400 |
$2,190
41,319
kWh
|
$605
-
kW-mo/yr
|
|
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $2,436 | $760 |
$1,759
33,197
kWh
|
$677
-
kW-mo/yr
|
|
| 08 | 2.7221: Lower temperature during the winter season and vice-versa | $2,349 | $40 |
$1,840
34,726
kWh
|
$509
-
kW-mo/yr
|
|
| 09 | 2.2515: Use optimum thickness insulation | $2,315 | $320 |
$1,668
31,469
kWh
|
$647
-
kW-mo/yr
|
|
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,965 | $40 |
$1,286
24,259
kWh
|
$679
-
kW-mo/yr
|
|
| 11 | 2.4323: Use optimum size and capacity equipment | $1,742 | $4,691 |
$1,371
25,865
kWh
|
$371
-
kW-mo/yr
|
|
| 12 | 2.4239: Eliminate or reduce compressed air usage | $1,627 | $1,480 |
$1,245
23,499
kWh
|
$382
-
kW-mo/yr
|
|
| 13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,603 | $1,660 |
$1,285
24,254
kWh
|
$318
-
kW-mo/yr
|
|
| 14 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $744 | $2,400 |
$744
14,040
kWh
|
- | |
| 15 | 2.7447: Install vinyl strip / high speed / air curtain doors | $286 | $605 |
$222
4,197
kWh
|
$64
-
kW-mo/yr
|
|
| 16 | 2.7111: Reduce illumination to minimum necessary levels | $115 | $320 |
$83
1,572
kWh
|
$32
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $42,139 | $48,730 |
$35,316
666,363
kWh
|
$6,823
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $22,110 | $28,584 |
$17,460
329,436
kWh
|
$4,650
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs