Assessment Year | 2015 |
---|---|
Principal Product | Machinery Manufacturing |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
250,000
ft2
|
Annual Production | 305
pieces
|
Production Hrs. Annual | 2,184
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $326,200 | 4,866,000 |
kWh
|
$0.067 |
Electricity Demand | $142,678 | 13,932 |
kW-mo/yr
|
$10.24 |
Natural Gas | $7,870 | 2,710 |
MMBtu
|
$2.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $280,805 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $83,053 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2628: Utilize a less expensive cooling method | $103,740 | $220,000 |
$40,853
608,837
kWh
|
$34,287
-
kW-mo/yr
|
- | $28,600 | |
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $94,012 | $102,610 |
$35,083
532,635
kWh
|
$58,929
-
kW-mo/yr
|
- | - | |
03 | 2.7425: Clean or color roof to reduce solar load | $45,923 | $79,106 |
$24,960
372,540
kWh
|
$20,963
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,431 | $9,248 |
$6,758
100,870
kWh
|
$5,673
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,235 | $1,660 |
$6,114
91,122
kWh
|
$5,121
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $4,706 | $2,901 |
$4,706
70,237
kWh
|
- | - | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $2,804 | $480 |
$1,524
22,705
kWh
|
$1,280
-
kW-mo/yr
|
- | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $2,391 | $8,360 |
$1,300
19,396
kWh
|
$1,091
-
kW-mo/yr
|
- | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,181 | $40 |
$1,208
18,030
kWh
|
$973
-
kW-mo/yr
|
- | - | |
10 | 2.2515: Use optimum thickness insulation | $711 | $610 | - | - |
$711
-
MMBtu
|
- | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $671 | $1,880 |
$365
5,451
kWh
|
$306
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $280,805 | $426,895 |
$122,871
1,841,823
kWh
|
$128,623
-
kW-mo/yr
|
$711
-
MMBtu
|
$28,600 | ||
TOTAL IMPLEMENTED | $83,053 | $104,285 |
$46,935
700,351
kWh
|
$35,407
-
kW-mo/yr
|
$711
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs