| Assessment Year | 2015 |
|---|---|
| Principal Product | Clinical Laboratory Products |
| NAICS | 333249: Other Industrial Machinery Manufacturing |
| SIC | 3821: Laboratory Apparatus and Furniture |
| Sales Range | $50 M to 100M |
| # of Employees | 500 |
| Plant Area |
200,000
ft2
|
| Annual Production | 60,000,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $564,550 | 14,099,733 |
kWh
|
$0.040 |
| Electricity Demand | $404,083 | 25,999 |
kW-mo/yr
|
$15.54 |
| Electricity Fees | $183,681 | - |
|
- |
| Natural Gas | $6,846 | 423 |
MMBtu
|
$16.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $213,177 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,038 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $108,119 | $1,400 | - | - | - | $108,119 | - | |
| 02 | 2.2628: Utilize a less expensive cooling method | $59,120 | $60,000 |
$33,416
835,390
kWh
|
$17,904
-
kW-mo/yr
|
- | - | $7,800 | |
| 03 | 2.7425: Clean or color roof to reduce solar load | $21,227 | $27,707 |
$10,223
255,583
kWh
|
$11,004
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7221: Lower temperature during the winter season and vice-versa | $12,994 | $80 |
$8,471
211,769
kWh
|
$4,523
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.1332: Convert combustion equipment to burn natural gas | $4,265 | $11,000 | - | - | - | $4,265 | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $3,714 | $2,680 |
$2,004
50,097
kWh
|
$1,710
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7135: Install occupancy sensors | $1,059 | $373 |
$546
13,660
kWh
|
$513
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.7134: Use photocell controls | $1,053 | $360 |
$338
8,453
kWh
|
$715
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $811 | $3,060 |
$811
20,276
kWh
|
- | - | - | - | |
| 10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $727 | $2,044 |
$261
6,534
kWh
|
$466
-
kW-mo/yr
|
- | - | - | |
| 11 | 2.2515: Use optimum thickness insulation | $88 | $360 | - | - |
$88
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $213,177 | $109,064 |
$56,070
1,401,762
kWh
|
$36,835
-
kW-mo/yr
|
$88
-
MMBtu
|
$112,384 | $7,800 | ||
| TOTAL IMPLEMENTED | $22,038 | $30,767 |
$11,034
275,859
kWh
|
$11,004
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs