ITAC Assessment: MI0269
ITAC logo
ITAC Assessment: MI0269
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Quilting Machinery
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3552: Textile Machinery
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area 66,000
ft2
Annual Production 36
pieces
Production Hrs. Annual 2,730
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,918 1,137,960
kWh
Electricity Demand $30,487 2,737
kW-mo/yr
Electricity Fees $15,976 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $70,837 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $55,702

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.2628: Utilize a less expensive cooling method $33,693 $150,000 $10,985
211,257
kWh
$3,208
-
kW-mo/yr
$19,500
02 2.7425: Clean or color roof to reduce solar load $7,680 $15,839 $5,942
114,262
kWh
$1,738
-
kW-mo/yr
-
03 2.7496: Install partitions to reduce size of conditioned space $7,455 $22,478 $5,762
110,799
kWh
$1,693
-
kW-mo/yr
-
04 2.6218: Turn off equipment when not in use $4,584 $3,600 $4,584
88,154
kWh
- -
05 2.7447: Install vinyl strip / high speed / air curtain doors $3,528 $2,040 $2,726
52,416
kWh
$802
-
kW-mo/yr
-
06 2.7496: Install partitions to reduce size of conditioned space $3,491 $9,600 $2,689
51,706
kWh
$802
-
kW-mo/yr
-
07 2.7145: Install skylights $2,957 $500 $1,520
29,238
kWh
$1,437
-
kW-mo/yr
-
08 2.7141: Lower light fixtures in high ceiling areas $2,668 $6,886 $1,376
26,454
kWh
$1,292
-
kW-mo/yr
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $2,598 $2,160 $1,640
31,536
kWh
$958
-
kW-mo/yr
-
10 2.7132: Install timers on light switches in little used areas $1,064 $360 $1,064
20,467
kWh
- -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $928 $1,660 $728
14,000
kWh
$200
-
kW-mo/yr
-
12 3.5313: Increase amount of waste recovered for resale $140 $20 - - $140
13 2.7135: Install occupancy sensors $51 $80 $51
978
kWh
- -
TOTAL RECOMMENDED $70,837 $215,223 $39,067
751,267
kWh
$12,130
-
kW-mo/yr
$19,640
TOTAL IMPLEMENTED $55,702 $176,906 $27,363
526,206
kWh
$8,699
-
kW-mo/yr
$19,640
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs