| Assessment Year | 2013 |
|---|---|
| Principal Product | Pharmacutical |
| NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
| SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 100 |
| Plant Area |
55,000
ft2
|
| Annual Production | 300,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $184,859 | 3,622,324 |
kWh
|
$0.051 |
| Electricity Demand | $69,603 | 6,618 |
kW-mo/yr
|
$10.52 |
| Electricity Fees | $38,218 | - |
|
- |
| Natural Gas | $36,500 | 8,178 |
MMBtu
|
$4.46 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $61,051 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $53,934 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $30,416 | $2,300 |
$15,133
302,660
kWh
|
$15,283
-
kW-mo/yr
|
- | - | |
| 02 | 2.7425: Clean or color roof to reduce solar load | $14,747 | $17,000 |
$9,340
186,816
kWh
|
$5,407
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,442 | $1,660 |
$3,794
75,878
kWh
|
$1,648
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $2,851 | $417 |
$2,022
40,272
kWh
|
$829
-
kW-mo/yr
|
- | - | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,190 | $2,520 | - | - |
$2,190
-
MMBtu
|
- | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,076 | $6,910 |
$1,292
25,846
kWh
|
$784
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,508 | $4,420 |
$950
19,006
kWh
|
$558
-
kW-mo/yr
|
- | - | |
| 08 | 4.821: Pay bills on time to avoid late fees | $945 | $240 | - | - | - | $945 | |
| 09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $876 | $80 |
$681
13,620
kWh
|
$195
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $61,051 | $35,547 |
$33,212
664,098
kWh
|
$24,704
-
kW-mo/yr
|
$2,190
-
MMBtu
|
$945 | ||
| TOTAL IMPLEMENTED | $53,934 | $25,700 |
$29,898
597,980
kWh
|
$23,091
-
kW-mo/yr
|
- | $945 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs