ITAC Assessment: MI0241
ITAC logo
ITAC Assessment: MI0241
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Surgical appliances and supplies
NAICS 339113: Surgical Appliance and Supplies Manufacturing
SIC 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies
Sales Range $100
M
to 500
M
# of Employees 320
Plant Area 67,000
ft2
Annual Production 45
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,555 1,533,650
kWh
Electricity Demand $47,086 4,702
kW-mo/yr
Electricity Fees $32,831 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,009 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $55,394

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6218: Turn off equipment when not in use $16,509 $3,900 $13,204
240,068
kWh
$3,305
-
kW-mo/yr
02 2.6218: Turn off equipment when not in use $11,217 $6,000 $5,449
99,856
kWh
$5,768
-
kW-mo/yr
03 2.7221: Lower temperature during the winter season and vice-versa $9,040 $80 $5,845
106,271
kWh
$3,195
-
kW-mo/yr
04 2.7425: Clean or color roof to reduce solar load $7,960 $540 $6,368
115,789
kWh
$1,592
-
kW-mo/yr
05 2.4323: Use optimum size and capacity equipment $3,883 $4,691 $2,798
50,874
kWh
$1,085
-
kW-mo/yr
06 2.4323: Use optimum size and capacity equipment $2,564 $440 $570
10,356
kWh
$1,994
-
kW-mo/yr
07 2.4323: Use optimum size and capacity equipment $2,118 $5,397 $1,367
24,856
kWh
$751
-
kW-mo/yr
08 2.7447: Install vinyl strip / high speed / air curtain doors $1,942 $2,196 $947
17,233
kWh
$995
-
kW-mo/yr
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,593 $1,660 $1,528
27,788
kWh
$65
-
kW-mo/yr
10 2.4231: Reduce the pressure of compressed air to the minimum required $955 $80 $694
12,615
kWh
$261
-
kW-mo/yr
11 2.2511: Insulate bare equipment $686 $1,520 $336
6,112
kWh
$350
-
kW-mo/yr
12 2.7135: Install occupancy sensors $542 $209 $262
4,766
kWh
$280
-
kW-mo/yr
TOTAL RECOMMENDED $59,009 $26,713 $39,368
716,584
kWh
$19,641
-
kW-mo/yr
TOTAL IMPLEMENTED $55,394 $21,027 $37,045
674,347
kWh
$18,349
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs