ITAC Assessment: MI0237
ITAC logo
ITAC Assessment: MI0237
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Photographic and Optical Equipment/supplies Manufacturing
NAICS 333314: Optical Instrument and Lens Manufacturing
SIC 3827: Optical Instruments and Lenses
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 97,000
ft2
Annual Production 1,000
bushels
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $221,612 2,678,500
kWh
Electricity Demand $29,342 6,162
kW-mo/yr
Electricity Fees $38,406 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,023 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,241

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $22,474 $10,160 $20,241
243,870
kWh
$2,233
-
kW-mo/yr
02 2.7221: Lower temperature during the winter season and vice-versa $6,857 $80 $6,795
81,870
kWh
$62
-
kW-mo/yr
03 2.7496: Install partitions to reduce size of conditioned space $5,143 $2,188 $4,632
55,812
kWh
$511
-
kW-mo/yr
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,086 $80 $1,870
22,537
kWh
$216
-
kW-mo/yr
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,565 $1,660 $1,470
17,715
kWh
$95
-
kW-mo/yr
06 2.7447: Install vinyl strip / high speed / air curtain doors $1,104 $2,406 $994
11,983
kWh
$110
-
kW-mo/yr
07 2.7496: Install partitions to reduce size of conditioned space $1,045 $40 $940
11,326
kWh
$105
-
kW-mo/yr
08 2.7447: Install vinyl strip / high speed / air curtain doors $714 $205 $643
7,743
kWh
$71
-
kW-mo/yr
09 2.7496: Install partitions to reduce size of conditioned space $639 $1,240 $577
6,947
kWh
$62
-
kW-mo/yr
10 2.7496: Install partitions to reduce size of conditioned space $396 $1,880 $358
4,315
kWh
$38
-
kW-mo/yr
TOTAL RECOMMENDED $42,023 $19,939 $38,520
464,118
kWh
$3,503
-
kW-mo/yr
TOTAL IMPLEMENTED $36,241 $16,511 $33,311
401,359
kWh
$2,930
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs