Assessment Year | 2011 |
---|---|
Principal Product | Medical Instruments |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
170,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $401,112 | 7,040,000 |
kWh
|
$0.057 |
Electricity Demand | $125,105 | 12,940 |
kW-mo/yr
|
$9.67 |
Electricity Fees | $44,588 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $127,700 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $100,384 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7425: Clean or color roof to reduce solar load | $40,370 | $292,600 |
$27,940
465,667
kWh
|
$12,430
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $28,143 | $16,918 |
$21,384
356,414
kWh
|
$6,759
-
kW-mo/yr
|
|
03 | 2.7496: Install partitions to reduce size of conditioned space | $25,727 | $48,170 |
$19,548
325,793
kWh
|
$6,179
-
kW-mo/yr
|
|
04 | 2.7221: Lower temperature during the winter season and vice-versa | $16,075 | $2,550 |
$12,217
203,620
kWh
|
$3,858
-
kW-mo/yr
|
|
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $11,241 | $20,530 |
$8,543
142,388
kWh
|
$2,698
-
kW-mo/yr
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,355 | $1,320 |
$3,311
55,182
kWh
|
$1,044
-
kW-mo/yr
|
|
07 | 2.4239: Eliminate or reduce compressed air usage | $1,789 | $2,400 |
$1,364
22,715
kWh
|
$425
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $127,700 | $384,488 |
$94,307
1,571,779
kWh
|
$33,393
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $100,384 | $361,408 |
$73,547
1,225,771
kWh
|
$26,837
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs