Assessment Year | 2011 |
---|---|
Principal Product | Rubber Hardware |
NAICS | 326299: All Other Rubber Product Manufacturing |
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 110 |
Plant Area |
70,000
ft2
|
Annual Production | 10,800
pieces
|
Production Hrs. Annual | 2,678
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $77,075 | 1,238,185 |
kWh
|
$0.062 |
Electricity Demand | $36,687 | 4,266 |
kW-mo/yr
|
$8.60 |
Electricity Fees | $14,985 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,775 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,114 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,634 | $38,332 |
$10,874
175,383
kWh
|
$6,760
-
kW-mo/yr
|
|
02 | 2.2136: Install / repair insulation on steam lines | $8,973 | $1,984 |
$5,533
89,236
kWh
|
$3,440
-
kW-mo/yr
|
|
03 | 2.7496: Install partitions to reduce size of conditioned space | $4,980 | $18,280 |
$3,071
49,527
kWh
|
$1,909
-
kW-mo/yr
|
|
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,662 | $17,186 |
$2,873
46,337
kWh
|
$1,789
-
kW-mo/yr
|
|
05 | 2.7221: Lower temperature during the winter season and vice-versa | $3,114 | $2,500 |
$1,919
30,955
kWh
|
$1,195
-
kW-mo/yr
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,412 | $1,320 |
$870
14,031
kWh
|
$542
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $40,775 | $79,602 |
$25,140
405,469
kWh
|
$15,635
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $3,114 | $2,500 |
$1,919
30,955
kWh
|
$1,195
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs