Assessment Year | 2010 |
---|---|
Principal Product | Airplane |
NAICS | 336411: Aircraft Manufacturing |
SIC | 3721: Aircraft |
Sales Range | $100 M to 500M |
# of Employees | 450 |
Plant Area |
700,000
ft2
|
Annual Production | 300
pieces
|
Production Hrs. Annual | 4,335
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $636,510 | 12,815,564 |
kWh
|
$0.050 |
Electricity Demand | $178,678 | 39,732 |
kW-mo/yr
|
$4.50 |
Electricity Fees | $1,057,095 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $429,974 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $300,235 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.2628: Utilize a less expensive cooling method | $157,910 | $102,500 |
$145,494
996,537
kWh
|
$12,416
-
kW-mo/yr
|
|
02 | 2.7425: Clean or color roof to reduce solar load | $113,486 | $143,892 |
$104,565
716,196
kWh
|
$8,921
-
kW-mo/yr
|
|
03 | 2.7221: Lower temperature during the winter season and vice-versa | $108,082 | $2,000 |
$99,585
682,091
kWh
|
$8,497
-
kW-mo/yr
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $34,243 | $1,210 |
$32,605
223,321
kWh
|
$1,638
-
kW-mo/yr
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,467 | $40 |
$11,330
77,604
kWh
|
$1,137
-
kW-mo/yr
|
|
06 | 2.4323: Use optimum size and capacity equipment | $3,786 | $4,531 |
$3,609
24,717
kWh
|
$177
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $429,974 | $254,173 |
$397,188
2,720,466
kWh
|
$32,786
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $300,235 | $105,710 |
$277,684
1,901,949
kWh
|
$22,551
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs