ITAC Assessment: MI0196
ITAC logo
ITAC Assessment: MI0196
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Airplane
NAICS 336411: Aircraft Manufacturing
SIC 3721: Aircraft
Sales Range $100
M
to 500
M
# of Employees 450
Plant Area 700,000
ft2
Annual Production 300
pieces
Production Hrs. Annual 4,335
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $636,510 12,815,564
kWh
Electricity Demand $178,678 39,732
kW-mo/yr
Electricity Fees $1,057,095 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $429,974 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $300,235

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.2628: Utilize a less expensive cooling method $157,910 $102,500 $145,494
996,537
kWh
$12,416
-
kW-mo/yr
02 2.7425: Clean or color roof to reduce solar load $113,486 $143,892 $104,565
716,196
kWh
$8,921
-
kW-mo/yr
03 2.7221: Lower temperature during the winter season and vice-versa $108,082 $2,000 $99,585
682,091
kWh
$8,497
-
kW-mo/yr
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $34,243 $1,210 $32,605
223,321
kWh
$1,638
-
kW-mo/yr
05 2.4231: Reduce the pressure of compressed air to the minimum required $12,467 $40 $11,330
77,604
kWh
$1,137
-
kW-mo/yr
06 2.4323: Use optimum size and capacity equipment $3,786 $4,531 $3,609
24,717
kWh
$177
-
kW-mo/yr
TOTAL RECOMMENDED $429,974 $254,173 $397,188
2,720,466
kWh
$32,786
-
kW-mo/yr
TOTAL IMPLEMENTED $300,235 $105,710 $277,684
1,901,949
kWh
$22,551
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs