ITAC Assessment: OR0507
ITAC logo
ITAC Assessment: OR0507
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Dairy
NAICS 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing
SIC 2023: Dry, Condensed, and Evaporated Dairy Products
Sales Range $100
M
to 500
M
# of Employees 42
Plant Area 40,000
ft2
Annual Production 292,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $201,372 4,257,103
kWh
Electricity Demand $28,344 691
kW-mo/yr
Natural Gas $721,963 79,722
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $389,750 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $190,850

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Increase in Production Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $2,600 - $2,600
55,100
kWh
- - - - - - -
02 4.611: Begin a practice of predictive / preventative maintenance $46,800 $2,000 - - - - - - - $46,800
03 2.2128: Use steam condensate for hot water supply (non-potable) $13,600 $3,200 - - - $13,600
-
MMBtu
- - - -
04 2.1232: Keep boiler tubes clean $13,700 $4,000 - - - $13,700
-
MMBtu
- - - -
05 4.652: Replace existing equipment with more suitable substitutes $40,000 $1,500 - - - - - - - $40,000
06 4.451: Add additional production shift $60,100 $41,100 - - - - - $60,100 - -
07 2.2511: Insulate bare equipment $1,600 $1,200 - - - $1,600
-
MMBtu
- - - -
08 3.4114: Replace city water with recycled water via cooling tower $32,400 $23,200 - - - - $32,400
-
Tgal
- - -
09 2.7135: Install occupancy sensors $2,100 $2,100 $1,540
32,000
kWh
- - - - - $560 -
10 2.4145: Install isolation transformer on adjustable frequency drive $22,760 $24,900 $20,260
424,800
kWh
$2,500
-
kW-mo/yr
- - - - - -
11 2.2621: Modify refrigeration system to operate at a lower pressure $1,800 $2,600 $1,800
37,400
kWh
- - - - - - -
12 4.111: Add equipment/ operators to reduce production bottleneck $61,100 $85 - - - - - $38,600 - $22,500
13 2.3212: Optimize plant power factor $6,600 $10,500 - - $6,600 - - - - -
14 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,300 $5 $2,300
49
kWh
- - - - - - -
15 2.4133: Use most efficient type of electric motors $4,890 $19,200 $4,344
94,100
kWh
$546
-
kW-mo/yr
- - - - - -
16 2.2414: Use waste heat from hot flue gases to preheat $77,400 $330,000 $(-3,100.0)
(-64,500)
kWh
$(-400.0)
-
kW-mo/yr
- $80,900
-
MMBtu
- - - -
TOTAL RECOMMENDED $389,750 $465,590 $29,744
578,949
kWh
$2,646
-
kW-mo/yr
$6,600 $109,800
-
MMBtu
$32,400
-
Tgal
$98,700 $560 $109,300
TOTAL IMPLEMENTED $190,850 $92,700 $27,204
574,000
kWh
$3,046
-
kW-mo/yr
- $13,700
-
MMBtu
- $60,100 - $86,800
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs