Assessment Year | 2010 |
---|---|
Principal Product | Aircraft Parts & Equipment |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
204,000
ft2
|
Annual Production | 1,000
pieces
|
Production Hrs. Annual | 3,060
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $553,219 | 5,532,190 |
kWh
|
$0.10 |
Electricity Demand | $116,502 | 11,650 |
kW-mo/yr
|
$10.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $188,629 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $76,449 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $75,044 | $1,800 |
$53,904
539,040
kWh
|
$21,140
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $63,336 | $80,304 |
$45,496
454,962
kWh
|
$17,840
-
kW-mo/yr
|
|
03 | 2.7425: Clean or color roof to reduce solar load | $32,237 | $65,613 |
$23,157
231,568
kWh
|
$9,080
-
kW-mo/yr
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,923 | $1,210 |
$6,413
64,128
kWh
|
$2,510
-
kW-mo/yr
|
|
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,899 | $3,903 |
$3,519
35,188
kWh
|
$1,380
-
kW-mo/yr
|
|
06 | 2.7221: Lower temperature during the winter season and vice-versa | $4,190 | $2,000 |
$3,010
30,104
kWh
|
$1,180
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $188,629 | $154,830 |
$135,499
1,354,990
kWh
|
$53,130
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $76,449 | $83,514 |
$54,919
549,194
kWh
|
$21,530
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs