| Assessment Year | 2008 |
|---|---|
| Principal Product | Chicken Sausage |
| NAICS | 311613: Rendering and Meat Byproduct Processing |
| SIC | 2013: Sausages and Other Prepared Meat Products |
| Sales Range | $5 M to 10M |
| # of Employees | 82 |
| Plant Area |
16,000
ft2
|
| Annual Production | 9,000,000
lb
|
| Production Hrs. Annual | 3,250
hrs
|
| Location (State) | Puerto Rico |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $413,794 | 2,274,800 |
kWh
|
$0.18 |
| Electricity Demand | $122,497 | 15,108 |
kW-mo/yr
|
$8.11 |
| Electricity Fees | $2,400 | - |
|
- |
| Fuel Oil #6 | $104,730 | 7,093 |
MMBtu
|
$14.77 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $131,219 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $99,832 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $79,083 | $3,320 |
$67,907
373,321
kWh
|
$11,176
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,749 | $1,210 |
$16,070
88,346
kWh
|
$4,679
-
kW-mo/yr
|
- | |
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $19,089 | $3,928 |
$17,990
98,900
kWh
|
$1,099
-
kW-mo/yr
|
- | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $7,803 | $18,301 |
$6,098
33,519
kWh
|
$1,705
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,967 | $40 |
$2,359
12,971
kWh
|
$608
-
kW-mo/yr
|
- | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,528 | $1,240 | - | - |
$1,528
-
MMBtu
|
|
| TOTAL RECOMMENDED | $131,219 | $28,039 |
$110,424
607,057
kWh
|
$19,267
-
kW-mo/yr
|
$1,528
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $99,832 | $4,530 |
$83,977
461,667
kWh
|
$15,855
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs