Assessment Year | 2008 |
---|---|
Principal Product | Electroplated Switches |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
88,000
ft2
|
Annual Production | 4,223,000
pieces
|
Production Hrs. Annual | 4,625
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,019,618 | 7,244,820 |
kWh
|
$0.14 |
Electricity Demand | $181,523 | 17,551 |
kW-mo/yr
|
$10.34 |
Electricity Fees | $5,400 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $276,066 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $255,840 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $114,642 | $3,960 |
$96,118
686,529
kWh
|
$18,524
-
kW-mo/yr
|
|
02 | 2.7221: Lower temperature during the winter season and vice-versa | $80,047 | $6,886 |
$74,370
384,436
kWh
|
$5,677
-
kW-mo/yr
|
|
03 | 2.4322: Use or replace with energy efficient substitutes | $10,553 | $22,366 |
$8,855
63,242
kWh
|
$1,698
-
kW-mo/yr
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,799 | $40 |
$11,135
78,901
kWh
|
$1,664
-
kW-mo/yr
|
|
05 | 2.4323: Use optimum size and capacity equipment | $8,597 | $4,400 |
$8,288
58,724
kWh
|
$309
-
kW-mo/yr
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,466 | $1,032 |
$18,959
20,452
kWh
|
$1,507
-
kW-mo/yr
|
|
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,297 | $40 |
$6,676
47,305
kWh
|
$1,621
-
kW-mo/yr
|
|
08 | 2.4323: Use optimum size and capacity equipment | $5,657 | $4,400 |
$5,068
35,907
kWh
|
$589
-
kW-mo/yr
|
|
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,992 | $1,032 |
$7,595
53,815
kWh
|
$3,397
-
kW-mo/yr
|
|
10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,174 | $260 |
$2,884
20,438
kWh
|
$290
-
kW-mo/yr
|
|
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $842 | - |
$818
5,796
kWh
|
$24
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $276,066 | $44,416 |
$240,766
1,455,545
kWh
|
$35,300
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $255,840 | $17,390 |
$223,141
1,330,162
kWh
|
$32,699
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs