ITAC Assessment: MI0152
ITAC logo
ITAC Assessment: MI0152
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Trailer Truck Refrigerators
NAICS 423740: Refrigeration Equipment and Supplies Merchant Wholesalers
SIC 5078: Refrigeration Equipment and Supplies
Sales Range $10
M
to 50
M
# of Employees 385
Plant Area 176,000
ft2
Annual Production 23,750
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Puerto Rico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $826,619 5,907,990
kWh
Electricity Demand $147,153 19,091
kW-mo/yr
Electricity Fees $6,896 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $99,900 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,742

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $31,769 $1,074 $30,710
219,358
kWh
$1,059
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $29,086 $724 $28,075
200,537
kWh
$1,011
-
kW-mo/yr
-
03 2.6231: Utilize controls to operate equipment only when needed $18,314 $4,000 $17,370
173,710
kWh
$944
-
kW-mo/yr
-
04 4.821: Pay bills on time to avoid late fees $6,896 $300 - - $6,896
05 2.4231: Reduce the pressure of compressed air to the minimum required $5,287 $30 $4,419
31,567
kWh
$868
-
kW-mo/yr
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $4,557 $30 $3,941
28,151
kWh
$616
-
kW-mo/yr
-
07 2.4323: Use optimum size and capacity equipment $3,097 $3,010 $2,644
15,648
kWh
$453
-
kW-mo/yr
-
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $894 $510 $703
7,034
kWh
$191
-
kW-mo/yr
-
TOTAL RECOMMENDED $99,900 $9,678 $87,862
676,005
kWh
$5,142
-
kW-mo/yr
$6,896
TOTAL IMPLEMENTED $71,742 $5,618 $62,132
442,577
kWh
$2,714
-
kW-mo/yr
$6,896
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs