ITAC Assessment: MI0132
ITAC logo
ITAC Assessment: MI0132
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Plastic Sheet
NAICS 326130: Laminated Plastics Plate, Sheet (except Packaging), and Shape Manufacturing
SIC 3083: Laminated Plastics Plate, Sheet, and Profile Shapes
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 94,000
ft2
Annual Production 39,600,000
lb
Production Hrs. Annual 6,656
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $576,737 11,157,040
kWh
Electricity Demand $215 35
kW-mo/yr
Electricity Fees $72,987 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,865 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,160

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $49 $2,342 $40
548
kWh
$9
-
kW-mo/yr
02 2.4239: Eliminate or reduce compressed air usage $889 - $4
79
kWh
$885
-
kW-mo/yr
03 2.7261: Install timers and/or thermostats $222 $1,732 $11
232
kWh
$211
-
kW-mo/yr
04 2.7221: Lower temperature during the winter season and vice-versa $8 $23,253 $7
156
kWh
$1
-
kW-mo/yr
05 2.7221: Lower temperature during the winter season and vice-versa $697 $20,253 $3
61
kWh
$694
-
kW-mo/yr
TOTAL RECOMMENDED $1,865 $47,580 $65
1,076
kWh
$1,800
-
kW-mo/yr
TOTAL IMPLEMENTED $1,160 $4,074 $55
859
kWh
$1,105
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs