Assessment Year | 2018 |
---|---|
Principal Product | Steering Columns |
NAICS | 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 495 |
Plant Area |
200,000
ft2
|
Annual Production | 3,000,000
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $291,491 | 6,554,640 |
kWh
|
$0.044 | |
Electricity Demand | $166,229 | 13,907 |
kW-mo/yr
|
$11.95 | |
Natural Gas | $8,625 | 1,717 |
MMBtu
|
$5.02 | |
Waste Disposal Costs | |||||
Water Usage | $5,497 | 134,126 |
Tgal
|
$0.041 | |
Water Disposal | $6,457 | 134 |
Tgal
|
$48.14 | |
TOTAL YEARLY COSTS | $478,299 | ||||
RECOMMENDED SAVINGS* | $58,470 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $23,488 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2615: Clean condenser tubes | $14,316 | $600 |
$14,316
318,129
kWh
|
- | - | |
02 | 2.4235: Remove or close off unneeded compressed air lines | $13,850 | $17,000 |
$9,289
208,744
kWh
|
$4,561
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,088 | $2,000 |
$7,088
159,283
kWh
|
- | - | |
04 | 2.3212: Optimize plant power factor | $6,114 | $5,200 | - |
$6,114
-
kW-mo/yr
|
- | |
05 | 2.4235: Remove or close off unneeded compressed air lines | $5,157 | - |
$5,157
115,877
kWh
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,604 | $3,500 |
$2,995
67,320
kWh
|
$1,609
-
kW-mo/yr
|
- | |
07 | 4.232: Lease equipment instead of purchasing | $3,120 | - | - | - | $3,120 | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,744 | $5,280 |
$1,744
39,192
kWh
|
- | - | |
09 | 2.4239: Eliminate or reduce compressed air usage | $1,382 | $1,000 |
$1,382
31,056
kWh
|
- | - | |
10 | 2.6218: Turn off equipment when not in use | $755 | $2,000 |
$755
16,968
kWh
|
- | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $340 | $465 |
$169
3,802
kWh
|
$62
-
kW-mo/yr
|
$109 | |
TOTAL RECOMMENDED | $58,470 | $37,045 |
$42,895
960,371
kWh
|
$12,346
-
kW-mo/yr
|
$3,229 | ||
TOTAL IMPLEMENTED | $23,488 | $8,345 |
$23,317
520,406
kWh
|
$62
-
kW-mo/yr
|
$109 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs