| Assessment Year | 2006 |
|---|---|
| Principal Product | Wooden Doors, Kitchen Cabinets |
| NAICS | 321911: Wood Window and Door Manufacturing |
| SIC | 2431: Millwork |
| Sales Range | $10 M to 50M |
| # of Employees | 129 |
| Plant Area |
86,000
ft2
|
| Annual Production | 80,000
pieces
|
| Production Hrs. Annual | 2,200
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $58,528 | 1,051,860 |
kWh
|
$0.056 |
| Electricity Demand | $38,833 | 4,930 |
kW-mo/yr
|
$7.88 |
| Electricity Fees | $12,163 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,477 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4323: Use optimum size and capacity equipment | $18,965 | $5,163 |
$10,574
190,106
kWh
|
$8,391
-
kW-mo/yr
|
|
| 02 | 2.4323: Use optimum size and capacity equipment | $15,874 | $3,709 |
$7,182
129,116
kWh
|
$8,692
-
kW-mo/yr
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,318 | $1,074 |
$3,273
58,843
kWh
|
$2,045
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,569 | $1,074 |
$2,214
39,808
kWh
|
$1,355
-
kW-mo/yr
|
|
| 05 | 2.4321: Upgrade obsolete equipment | $1,134 | $28 |
$599
10,773
kWh
|
$535
-
kW-mo/yr
|
|
| 06 | 2.4321: Upgrade obsolete equipment | $1,085 | $28 |
$540
10,773
kWh
|
$545
-
kW-mo/yr
|
|
| 07 | 2.4221: Install compressor air intakes in coolest locations | $685 | $260 |
$405
7,256
kWh
|
$280
-
kW-mo/yr
|
|
| 08 | 2.4323: Use optimum size and capacity equipment | $602 | $940 |
$334
6,012
kWh
|
$268
-
kW-mo/yr
|
|
| 09 | 2.4323: Use optimum size and capacity equipment | $245 | $940 |
$134
2,416
kWh
|
$111
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $47,477 | $13,216 |
$25,255
455,103
kWh
|
$22,222
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs