| Assessment Year | 2005 |
|---|---|
| Principal Product | Metal Patio Furniture |
| NAICS | 337124: Metal Household Furniture Manufacturing |
| SIC | 2514: Metal Household Furniture |
| Sales Range | $10 M to 50M |
| # of Employees | 275 |
| Plant Area |
80,000
ft2
|
| Annual Production | 230,000
pieces
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $95,718 | 1,886,880 |
kWh
|
$0.051 |
| Electricity Demand | $66,793 | 8,103 |
kW-mo/yr
|
$8.24 |
| Electricity Fees | $3,190 | - |
|
- |
| Natural Gas | $83,432 | 11,919 |
MMBtu
|
$7.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,643 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $14,993 | $9,230 |
$12,170
239,891
kWh
|
$2,823
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $8,966 | $4,628 | - | - |
$8,966
-
MMBtu
|
- | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $6,306 | $65 |
$4,483
88,351
kWh
|
$1,823
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,896 | $862 |
$3,641
71,777
kWh
|
$591
-
kW-mo/yr
|
- | $(-336.0) | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,613 | $56 |
$1,468
28,944
kWh
|
$1,145
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $1,808 | $84 |
$1,808
35,701
kWh
|
- | - | - | - | |
| 07 | 4.821: Pay bills on time to avoid late fees | $1,061 | - | - | - | - | - | $1,061 | |
| TOTAL RECOMMENDED | $39,643 | $14,925 |
$23,570
464,664
kWh
|
$6,382
-
kW-mo/yr
|
$8,966
-
MMBtu
|
$(-336.0) | $1,061 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs