ITAC Assessment: KG0034
ITAC logo
ITAC Assessment: KG0034
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Nursing Home and Steel Dormitory Furniture;Furniture and Fix
NAICS
n/a
SIC 2531: Public Building and Related Furniture
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 140,000
ft2
Annual Production 40,000
lb
Production Hrs. Annual 4,914
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,930 1,189,918
kWh
Natural Gas $52,363 18,237
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,046 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,463

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $6,463 $9,895 $6,463
132,181
kWh
-
02 2.2511: Insulate bare equipment $4,916 $7,945 - $4,916
-
MMBtu
03 2.6231: Utilize controls to operate equipment only when needed $917 $450 $917
27,843
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $750 $408 $750
14,654
kWh
-
TOTAL RECOMMENDED $13,046 $18,698 $8,130
174,678
kWh
$4,916
-
MMBtu
TOTAL IMPLEMENTED $6,463 $9,895 $6,463
132,181
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs