| Assessment Year | 2005 |
|---|---|
| Principal Product | Newspaper Printing |
| NAICS | 511110: Newspaper Publishers |
| SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
| Sales Range | $50 M to 100M |
| # of Employees | 450 |
| Plant Area |
280,000
ft2
|
| Annual Production | 120,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,321,159 | 27,003,183 |
kWh
|
$0.049 |
| Electricity Demand | $328,346 | 60,195 |
kW-mo/yr
|
$5.45 |
| Electricity Fees | $279,515 | - |
|
- |
| Natural Gas | $36,904 | 4,896 |
MMBtu
|
$7.54 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $180,238 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $81,540 | $120,000 |
$81,540
1,430,800
kWh
|
- | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $44,261 | $320 |
$31,678
500,164
kWh
|
$12,583
-
kW-mo/yr
|
- | |
| 03 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $26,325 | $32,000 | - | - |
$26,325
-
MMBtu
|
|
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $16,112 | - |
$13,618
283,617
kWh
|
$2,494
-
kW-mo/yr
|
- | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $7,381 | $14,100 |
$7,381
147,620
kWh
|
- | - | |
| 06 | 2.7122: Disconnect ballasts | $4,619 | - |
$4,619
39,648
kWh
|
- | - | |
| TOTAL RECOMMENDED | $180,238 | $166,420 |
$138,836
2,401,849
kWh
|
$15,077
-
kW-mo/yr
|
$26,325
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs