Assessment Year | 2000 |
---|---|
Principal Product | Pine Lumber |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $1 M to 5M |
# of Employees | 45 |
Plant Area |
43,070
ft2
|
Annual Production | 8,000,000
thousand feet
|
Production Hrs. Annual | 2,350
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,014 | 1,976,846 |
kWh
|
$0.088 |
Electricity Demand | $6,031 | 7,758 |
kW-mo/yr
|
$0.78 |
Electricity Fees | $469 | - |
|
- |
Fuel Oil #2 | $3,111 | 447 |
MMBtu
|
$6.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $121,262 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,632 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $35,240 | $66,900 |
$35,240
497,069
kWh
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,062 | $5,845 |
$1,542
19,637
kWh
|
$520
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,392 | $340 |
$1,392
19,637
kWh
|
- | - | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $241 | $450 |
$241
3,517
kWh
|
- | - | - | - | |
05 | 2.2123: Insulate feedwater tank | $88 | $250 | - | - |
$88
-
MMBtu
|
- | - | |
06 | 3.1192: Reduce scrap production | $61,470 | $204,600 | - | - | - |
$(-3,330.0)
-
lb
|
$64,800 | |
07 | 4.114: Add/modify equipment to improve drying process | $20,769 | - | - | - | - | - | $20,769 | |
TOTAL RECOMMENDED | $121,262 | $278,385 |
$38,415
539,860
kWh
|
$520
-
kW-mo/yr
|
$88
-
MMBtu
|
$(-3,330.0)
-
lb
|
$85,569 | ||
TOTAL IMPLEMENTED | $36,632 | $67,240 |
$36,632
516,706
kWh
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs