ITAC Assessment: NC0002
ITAC logo
ITAC Assessment: NC0002
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Steel
NAICS
n/a
SIC 3399: Primary Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 171,000
ft2
Annual Production 0
units
Production Hrs. Annual 4,500
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $108,363 1,884,818
kWh
Natural Gas $46,066 10,771
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,855 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,763

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $566 $522 $566
9,379
kWh
02 2.7144: Install spectral reflectors / delamp $3,351 $120 $3,351
57,737
kWh
03 2.4235: Remove or close off unneeded compressed air lines $1,991 $1,209 $1,991
34,291
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,206 $100 $1,206
20,809
kWh
05 2.7145: Install skylights $5,957 $9,715 $5,957
102,579
kWh
06 2.7491: Insulate glazing, walls, ceilings, and roofs $17,784 $39,880 $17,784
1,371,630
kWh
TOTAL RECOMMENDED $30,855 $51,546 $30,855
1,596,425
kWh
TOTAL IMPLEMENTED $3,763 $1,831 $3,763
64,479
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs